|   Neg #   |  
 Title   |   Progress  |  
 Acc. #  | 
 |   270  |  
 Pier 9 North, Cherry Street; Bulkhead section, looking south. July 20, 1917  |  
 Work completed to date: 10.16% Contract No. 283  |  
 P.9260.97  | 
 |   284  |  
 Pier No. 9 North, Cherry Street; Bulkhead section, looking north. August 21, 
1917  |   Work completed to date: 11.90%. 
Contract No.283  |   P.9260.98  | 
 
|   305  |  
 Pier No. 9 North, Cherry Street; Bulkhead section, looking north. October 20, 
1917  |   Work completed to date: 13.26%. 
Contract No. 283  |   P.9260.99  | 
 
|   316  |  
 Pier No. 9 North, Cherry Street; Bulkhead section, looking north. December 
4, 1917  |   Work completed to date: 
13.67%. Contract No. 283  |   P.9260.100  | 
 
|   317  |  
 Pier No. 9 North, Cherry Street; Looking south, showing piling, etc. December 
4, 1917  |   Work completed to date: 
13.67%. Contract No. 283  |   P.9260.101  | 
 
|   323  |  
 Pier No. 9 North, Cherry Street; Bulkhead Section, looking north. January 31, 
1918  |   Work completed to date: 14.40%. 
Contract No. 283  |   P.9260.102  | 
 
|   326  |  
 Pier No. 9 North, Bulkhead Section, looking northeast. March 6, 1918  |  
 Work completed to date: 14.40%. Contract No. 283  |  
 P.9260.103  | 
 |   331  |  
 Pier No. 9 North, Bulkhead Section, looking northeast. March 28, 1918  |  
 Work completed to date: 15.10%. Contract No. 283  |  
 P.9260.104  | 
 |   344  |  
 Pier No. 9 North, looking east, showing forms, piling, etc. May 28, 1918  |  
 Work completed to date: 19.67%. Contract No. 283  |  
 P.9260.105  | 
 |   345  |  
 Pier No. 9 North, looking southeast showing forms, piling, etc. May 28, 1918  |  
 Work completed to date: 19.67%. Contract No. 283  |  
 P.9260.106  | 
 |   346  |  
 Pier No. 9 North, looking south showing forms and bulkhead. May 28, 1918  |  
 Work completed to date: 19.67%. Contract No. 283  |  
 P.9260.107  | 
 |   357  |  
 Pier No. 9 North, looking east, showing piling, clamps, etc. June 25, 1918  |  
 Work completed to date: 21.41%. Contract 382 (sic: No.283)  |  
 P.9260.108  | 
 |   358  |  
 Pier No. 9 North, looking northeast, showing piling, clamps, etc. June 25, 
1918  |   Work completed to date: 21.41%. 
Contract No. 283  |   P.9260.109  | 
 
|   360  |  
 Pier No. 9 North, looking east, showing concrete reinforcement under car tracks, 
etc. June 25, 1918  |   Work completed 
to date: 21.41%. Contract No. 283  |  
 P.9260.110  | 
 |   376  |  
 Pier No. 9 North, looking east, showing forms, piling etc. July 19, 1918  |  
 Work completed to date: 39.49%. Contract No. 283  |  
 P.9260.111  | 
 |   375  |  
 Pier No. 9 North, concrete deck, inshore end of pier, looking east.   July 
19, 1918  |   Work completed to date: 
39.49%. Contract No. 283  |   P.9260.112  | 
 
|   377  |  
 Pier No. 9 North, south side looking north. August 21, 1918  |  
 Work completed to date: 31.58%. Contract No. 283  |  
 P.9260.113  | 
 |   379  |  
 Pier No. 9 North, looking east, showing piling, clamps, etc. August 21, 1918  |  
 Work completed to date: 31.58%. Contract No. 283  |  
 P.9260.114  | 
 |   380  |  
 Pier No. 9 North, looking west, showing concrete forms and reinforcement. August 
21, 1918  |   Work completed to date: 
31.58%. Contract No. 283  |   P.9260.115  | 
 
|   381  |  
 Pier No. 9 North, superstructure inshore end. August 21, 1918  |  
 Work completed to date: 31.58%. Contract No. 283  |  
 P.9260.116  | 
 |   390  |  
 Pier No. 9 North, driving spur piles looking southeast, September 25, 1918  |  
 Work completed to date ... 38.01%. Contract No. 283  |  
 P.9260.117  | 
 |   393  |  
 Pier No. 9 North, inshore end showing concrete form, etc., September 25, 1918  |  
 Work completed to date: 38.01%. Contract No. 283  |  
 P.9260.118  | 
 |   394  |  
 Pier No. 9 North, south side looking northeast. September 25, 1918  |  
 Work completed to date: 38.01%. Contract No. 283  |  
 P.9260.119  | 
 |   395  |  
 Pier No. 9 North, looking west, inshore end. October 29, 1918  |  
 Work completed to date: 41.68%. Contract No. 283  |  
 P.9260.120  | 
 |   396  |  
 Pier No. 9 North, looking northeast, showing reinforcement and forms for deck 
slab. October 29, 1918  |   Work completed 
to date: 41.68%. Contract No. 283  |  
 P.9260.121  | 
 |   403  |  
 Pier No. 9 North, inshore end looking northeast. November 26, 1918  |  
 Work completed to date: 52.40%. Contract No. 283  |  
 P.9260.122  | 
 |   404  |  
 Pier No. 9 North, looking east showing piling, clamps, etc. November 26, 1918  |  
 Work completed to date: 52.40%. Contract No. 283  |  
 P.9260.123  | 
 |   416  |  
 Pier No. 9 North, inshore end, looking northeast. January 14, 1919  |  
 Work completed to December 20, 1918: 57.03%. Contract No. 283  |  
 P.9260.124  | 
 |   448  |  
 Pier No. 9 North, inshore end looking east. February 27, 1919  |  
 Work completed to date: 70.47%. Contract No. 283  |  
 P.9260.125  | 
 |   449  |  
 Pier No. 9 North, interior, looking east. February 27, 1919  |  
 Work completed to date: 70.47%. Contract No. 283  |  
 P.9260.126  | 
 |   455  |  
 Pier No. 9 North, outer end looking south. March 31, 1919  |  
 Work completed to date: 78.13%. Contract No. 283  |  
 P.9260.127  | 
 |   474  |  
 Pier No. 9 North, Cherry Street; outer end, looking southwest. May 27, 1919  |  
 Work completed to date: 90.69%. Contract No. 283  |  
 P.9260.128  | 
 |   475  |  
 Pier No. 9 North, Cherry Street; interior, looking east. May 27, 1919  |  
 Work completed to date: 90.69%. Contract No. 283  |  
 P.9260.129  | 
 |   497  |  
 Municipal Pier No. 9 North, Cherry Street; outshore end on north side.   
August 12, 1919  |   [Work complete]. 
Department of Wharves, Docks and Ferries, Philadelphia  |  
 P.9260.130  | 
 |   510  |  
 Municipal Pier No. 9 North, Cherry Street; inshore end. August 22, 1919  |  
 [Work complete].  Department of Wharves, Docks and Ferries, Philadelphia  |  
 P.9260.131  | 
 |   516  |  
 Municipal Pier No. 9 North, Cherry Street; outshore and looking west.   
September 9, 1919  |   [Work complete].  
Department of Wharves, Docks and Ferries, Philadelphia, Pa.  |  
 P.9260.132  | 
 |   520  |  
 Municipal Pier No. 9 North - Cherry Street, inshore end. September 11, 1919  |  
 [Work complete].  Department of Wharves, Docks and Ferries, Philadelphia  |  
 P.9260.133  | 
 |   226  |  
 Pier 78, South Delaware Wharves, north side, looking east, showing earth fill. 
March 28, 1917  |   Work completed 
to date: 65.0%. Date of completion 18 months from February 16, 1916. Contract 
No. 244  |   P.9260.134  | 
 |  
 370  |   Pier 78 South; superstructure, 
inshore end, looking southeast. July 19, 1918  |  
 [work] completed to date: 95%. Contract No. 250  |  
 P.9260.135  | 
 |   406  |  
 Municipal Pier 78, south Delaware wharves, McKean Street, outshore end, looking 
northwest. December 9, 1918  |  |  
 P.9260.136  | 
 |   347  |  
 Pier 80 South; storage of steel for superstructure of Pier 9 North (Cherry 
Street). May 28, 1918  |  |  
 P.9260.137  | 
 |   530  |  
 Pier 82 South; driving piles, looking east. September 25, 1919  |  
 Work completed to date: 5.32%. Contract No. 344  |  
 P.9260.138  | 
 |   531  |  
 Pier 82 South; bulkhead north of pier, looking north. September 25, 1919  |  
 Work completed to date: 5.32%. Contract No. 344  |  
 P.9260.139  | 
 |   570  |  
 Pier 82 South; bulkhead north, looking northeast. November 21, 1919  |  
 Work completed to date: 12.20%. Contract No. 344  |  
 P.9260.140  | 
 |   598  |  
 Pier 82 South; piling north side, looking east. March 11, 1920  |  
 Work completed to March 20: 19.27% Contract No. 344  |  
 P.9260.141  | 
 |   720  |  
 Pier 82 South; piling, etc., north side, looking east. January 13, 1921  |  
 Work completed to January 20: 28.29%. Contract No. 344  |  
 P.9260.142  | 
 |   764  |  
 Pier 82 South; clamps, caps, piles, etc., looking east, south side. April 26, 
1921  |   Materials in place April 20th: 
45.56%. Contract No. 344  |   P.9260.143  | 
 
|   817  |  
 Pier 82 South; bulkhead north of pier, looking west. July 20, 1921  |  
 Work completed to date: 78.68%. Contract No. 344  |  
 P.9260.144  | 
 |   818  |  
 Pier 82 South; south side of pier, bulkhead, etc., looking east. July 20, 1921  |  
 Work completed to date: 78.68%. Contract No. 344  |  
 P.9260.145  | 
 |   489  |  
 Pier 84 South; bulkhead section south of pier. June 20, 1919  |  
 Work completed to date: 2.62%. Contract No. 345  |  
 P.9260.146  | 
 |   506  |  
 Pier 84 South; bulkhead south of pier, looking north. August 21, 1919  |  
 Work completed to date: 12.2%. Contract No. 345  |  
 P.9260.147  | 
 |   507  |  
 Pier 84 South; looking northeast over site; showing dredge and pile drivers 
at work. August 21, 1919  |  |  
 P.9260.148  | 
 |   508  |  
 Pier 84 South; Ritner Street sewer, looking northeast, showing piling, etc. 
August 21, 1919  |   Work completed 
to date: 12.2%. Contract No. 345  |   P.9260.149  | 
 
|   526  |  
 Pier 84 South; bulkhead south of pier, looking north. Sept. 25, 1919  |  
 Work completed to date: 18.16%. Contract No. 345  |  
 P.9260.150  | 
 |   527  |  
 Pier 84 South; looking northeast, showing piling south side of pier. Sept. 
25, 1919  |   Work completed to date: 
18.16%. Contract No. 345  |   P.9260.151  | 
 
|   528  |  
 Pier 84 South; Ritner Street sewer, looking east. Sept. 25, 1919  |  
 Work completed to date: 18.16%. Contract No. 345  |  
 P.9260.152  | 
 |   546  |  
 Pier 84 South; bulkhead south of pier, looking north. Oct. 30, 1919  |  
 Work completed to Oct. 20: 21.08%. Contract No. 345  |  
 P.9260.153  | 
 |   569  |  
 Pier 84 South; looking northeast, showing piling, south side. Nov. 21, 1919  |  
 Work completed to date: 25.00%. Contract No. 345  |  
 P.9260.154  | 
 |   593  |  
 Pier 84 South; showing piling for tracks of pile cutting machine. Mar. 11, 
1920  |   Work completed to March 20: 
32.92%. Contract 345  |   P.9260.155  | 
 
|   594  |  
 Pier 84 South; driving spur piles, south side, and framing. Mar. 11, 1920  |  
 Work completed to March 20: 32.92%. Contract 345  |  
 P.9260.156  | 
 |   595  |  
 Pier 84 South; platforms south side of pier, and bulkhead looking southeast, 
Mar. 11, 1920  |   Work completed to 
March 20: 32.92%. Contract 345  |   P.9260.157  | 
 
|   596  |  
 Pier 84 South; showing joining of platforms, south side of pier bulkhead, top 
view. Mar. 11, 1920  |   Work completed 
to March 20: 32.92%. Contract 345  |  
 P.9260.158  | 
 |   597  |  
 Pier 84 South; Ritner Street sewer, looking northeast. Mar. 11, 1920  |  
 Work completed to March 20: 32.92%. Contract 345  |  
 P.9260.159  | 
 |   637  |  
 Pier 84 South; south side, looking northwest; machine cutting off spur piles. 
June 24, 1920  |   Work completed to 
June 20: 43.83%. Contract No. 345  |  
 P.9260.160  | 
 |   638  |  
 Pier 84 South; bulkhead, south side; concrete forms, etc., June 24, 1920  |  
 Work completed to June 20: 43.83%. Contract No. 345  |  
 P.9260.161  | 
 |   639  |  
 Pier 84 South; bulkhead, south side, looking southwest. June 24, 1920  |  
 Work completed to June 20: 43.83%. Contract No. 345  |  
 P.9260.162  | 
 |   640  |  
 Pier 84 South; platform and bulkhead, south side of pier, looking east. June 
24, 1920  |   Work completed to June 
20: 43.83%. Contract No. 345  |   P.9260.163  | 
 
|   641  |  
 Pier 84 South; driving spur piles, south side of pier, June 24, 1920  |  
 Work completed to June 20: 43.83%. Contract No. 345  |  
 P.9260.164  | 
 |   658  |  
 Pier 84 South; irregular steel form, looking north. July 27, 1920  |  
 Work completed to July 20: 48.22%. Contract No. 345  |  
 P.9260.166  | 
 |   659  |  
 Pier 84 South; showing earth fill in center of pier, looking east. July 27, 
1920  |   Work completed to July 20: 
48.22%. Contract No. 345  |   P.9260.167  | 
 
|   717  |  
 Pier 84 South; concrete cross wall, south side. Jan. 13, 1921  |  
 Work completed to Jan. 20: 68.73%. Contract No. 345  |  
 P.9260.168  | 
 |   718  |  
 Pier 84 South; south side of pier, inshore end. Jan. 13, 1921  |  
 Work completed to Jan. 20: 68.73%. Contract No. 345  |  
 P.9260.169  | 
 |   719  |  
 Pier 84 South; Ritner Street sewer, looking east. Jan. 13, 1921  |  
 Work completed to Jan. 20: 68.73%. Contract No. 345  |  
 P.9260.170  | 
 |   730  |  
 Pier 84 South; piling north side, etc., looking east. Feb. 17, 1921  |  
 Material in place Jan. 20: 68.73%. Contract No. 345  |  
 P.9260.171  | 
 |   731  |  
 Pier 84 South; north side Pier 84 and south side Pier 82; piling etc., Feb. 
17, 1921  |   Material in place Jan. 
20: 68.73%. Contract No. 345  |   P.9260.172  | 
 
|   732  |  
 Pier 84 South; showing retaining wall south side, fill, etc. Feb. 17, 1921  |  
 Material in place Jan. 20: 68.73%. Contract No. 345  |  
 P.9260.173  | 
 |   759  |  
 Pier 84 South; retaining wall south side of pier. Apr. 26, 1921  |  
 Materials in place April 20: 79.93%. Contract No. 345  |  
 P.9260.174  | 
 |   760  |  
 Pier 84 South; forms for retaining wall, north side, outshore end. Apr. 26, 
1921  |   Materials in place April 20: 
79.93%. Contract No. 345  |   P.9260.175  | 
 
|   762  |  
 Pier 84 South; clamps, caps, piles, etc. north side and bulkhead, Apr. 26, 
1921  |   Materials in place April 20: 
79.93%. Contract No. 345  |   P.9260.176  | 
 
|   763  |  
 Pier 84 South; bulkhead north of pier; clamps, caps, piles, etc., Apr. 26, 
1921  |   Materials in place April 20: 
79.93%. Contract No. 345  |   P.9260.177  | 
 
|   809  |  
 Pier 84 South; sewer, bulkheads and north side of pier, June 20, 1921  |  
 Work completed to date: 93.88%. Contract 345  |  
 P.9260.178  | 
 |   811  |  
 Pier 84 South; bulkhead and north side of 84, inshore end, looking east. June 
20, 1921  |   Work completed to date: 
93.88%. Contract 345  |   P.9260.179  | 
 
|   812  |  
 Pier 84 South; retaining wall, north side, outshore end, looking west. June 
20, 1921  |   Work completed to date: 
93.88%. Contract 345  |   P.9260.180  | 
 
|   819  |  
 Pier 84 South; bulkhead between piers 82 and 84, looking east. July 20, 1921  |  
 Work completed to date: 96.95%. Contract 345  |  
 P.9260.181  | 
 |   820  |  
 Pier 84 South; north side, inshore end, platform, etc., looking north. July 
20, 1921  |   Work completed to date: 
96.95%. Contract 345  |   P.9260.182  | 
 
|   821  |  
 Pier 84 South; north side, bulkhead, sewer, etc., looking north. July 20, 1921  |  
 Work completed to date: 96.95%. Contract 345  |  
 P.9260.183  | 
 |   1188  |  
 Pier 84 South; Porter Street, 1921  |  
 Work complete.  |   P.9260.184  |