Neg # |
Title | Progress |
Acc. # |
270 |
Pier 9 North, Cherry Street; Bulkhead section, looking south. July 20, 1917 |
Work completed to date: 10.16% Contract No. 283 |
P.9260.97 |
284 |
Pier No. 9 North, Cherry Street; Bulkhead section, looking north. August 21,
1917 | Work completed to date: 11.90%.
Contract No.283 | P.9260.98 |
305 |
Pier No. 9 North, Cherry Street; Bulkhead section, looking north. October 20,
1917 | Work completed to date: 13.26%.
Contract No. 283 | P.9260.99 |
316 |
Pier No. 9 North, Cherry Street; Bulkhead section, looking north. December
4, 1917 | Work completed to date:
13.67%. Contract No. 283 | P.9260.100 |
317 |
Pier No. 9 North, Cherry Street; Looking south, showing piling, etc. December
4, 1917 | Work completed to date:
13.67%. Contract No. 283 | P.9260.101 |
323 |
Pier No. 9 North, Cherry Street; Bulkhead Section, looking north. January 31,
1918 | Work completed to date: 14.40%.
Contract No. 283 | P.9260.102 |
326 |
Pier No. 9 North, Bulkhead Section, looking northeast. March 6, 1918 |
Work completed to date: 14.40%. Contract No. 283 |
P.9260.103 |
331 |
Pier No. 9 North, Bulkhead Section, looking northeast. March 28, 1918 |
Work completed to date: 15.10%. Contract No. 283 |
P.9260.104 |
344 |
Pier No. 9 North, looking east, showing forms, piling, etc. May 28, 1918 |
Work completed to date: 19.67%. Contract No. 283 |
P.9260.105 |
345 |
Pier No. 9 North, looking southeast showing forms, piling, etc. May 28, 1918 |
Work completed to date: 19.67%. Contract No. 283 |
P.9260.106 |
346 |
Pier No. 9 North, looking south showing forms and bulkhead. May 28, 1918 |
Work completed to date: 19.67%. Contract No. 283 |
P.9260.107 |
357 |
Pier No. 9 North, looking east, showing piling, clamps, etc. June 25, 1918 |
Work completed to date: 21.41%. Contract 382 (sic: No.283) |
P.9260.108 |
358 |
Pier No. 9 North, looking northeast, showing piling, clamps, etc. June 25,
1918 | Work completed to date: 21.41%.
Contract No. 283 | P.9260.109 |
360 |
Pier No. 9 North, looking east, showing concrete reinforcement under car tracks,
etc. June 25, 1918 | Work completed
to date: 21.41%. Contract No. 283 |
P.9260.110 |
376 |
Pier No. 9 North, looking east, showing forms, piling etc. July 19, 1918 |
Work completed to date: 39.49%. Contract No. 283 |
P.9260.111 |
375 |
Pier No. 9 North, concrete deck, inshore end of pier, looking east. July
19, 1918 | Work completed to date:
39.49%. Contract No. 283 | P.9260.112 |
377 |
Pier No. 9 North, south side looking north. August 21, 1918 |
Work completed to date: 31.58%. Contract No. 283 |
P.9260.113 |
379 |
Pier No. 9 North, looking east, showing piling, clamps, etc. August 21, 1918 |
Work completed to date: 31.58%. Contract No. 283 |
P.9260.114 |
380 |
Pier No. 9 North, looking west, showing concrete forms and reinforcement. August
21, 1918 | Work completed to date:
31.58%. Contract No. 283 | P.9260.115 |
381 |
Pier No. 9 North, superstructure inshore end. August 21, 1918 |
Work completed to date: 31.58%. Contract No. 283 |
P.9260.116 |
390 |
Pier No. 9 North, driving spur piles looking southeast, September 25, 1918 |
Work completed to date ... 38.01%. Contract No. 283 |
P.9260.117 |
393 |
Pier No. 9 North, inshore end showing concrete form, etc., September 25, 1918 |
Work completed to date: 38.01%. Contract No. 283 |
P.9260.118 |
394 |
Pier No. 9 North, south side looking northeast. September 25, 1918 |
Work completed to date: 38.01%. Contract No. 283 |
P.9260.119 |
395 |
Pier No. 9 North, looking west, inshore end. October 29, 1918 |
Work completed to date: 41.68%. Contract No. 283 |
P.9260.120 |
396 |
Pier No. 9 North, looking northeast, showing reinforcement and forms for deck
slab. October 29, 1918 | Work completed
to date: 41.68%. Contract No. 283 |
P.9260.121 |
403 |
Pier No. 9 North, inshore end looking northeast. November 26, 1918 |
Work completed to date: 52.40%. Contract No. 283 |
P.9260.122 |
404 |
Pier No. 9 North, looking east showing piling, clamps, etc. November 26, 1918 |
Work completed to date: 52.40%. Contract No. 283 |
P.9260.123 |
416 |
Pier No. 9 North, inshore end, looking northeast. January 14, 1919 |
Work completed to December 20, 1918: 57.03%. Contract No. 283 |
P.9260.124 |
448 |
Pier No. 9 North, inshore end looking east. February 27, 1919 |
Work completed to date: 70.47%. Contract No. 283 |
P.9260.125 |
449 |
Pier No. 9 North, interior, looking east. February 27, 1919 |
Work completed to date: 70.47%. Contract No. 283 |
P.9260.126 |
455 |
Pier No. 9 North, outer end looking south. March 31, 1919 |
Work completed to date: 78.13%. Contract No. 283 |
P.9260.127 |
474 |
Pier No. 9 North, Cherry Street; outer end, looking southwest. May 27, 1919 |
Work completed to date: 90.69%. Contract No. 283 |
P.9260.128 |
475 |
Pier No. 9 North, Cherry Street; interior, looking east. May 27, 1919 |
Work completed to date: 90.69%. Contract No. 283 |
P.9260.129 |
497 |
Municipal Pier No. 9 North, Cherry Street; outshore end on north side.
August 12, 1919 | [Work complete].
Department of Wharves, Docks and Ferries, Philadelphia |
P.9260.130 |
510 |
Municipal Pier No. 9 North, Cherry Street; inshore end. August 22, 1919 |
[Work complete]. Department of Wharves, Docks and Ferries, Philadelphia |
P.9260.131 |
516 |
Municipal Pier No. 9 North, Cherry Street; outshore and looking west.
September 9, 1919 | [Work complete].
Department of Wharves, Docks and Ferries, Philadelphia, Pa. |
P.9260.132 |
520 |
Municipal Pier No. 9 North - Cherry Street, inshore end. September 11, 1919 |
[Work complete]. Department of Wharves, Docks and Ferries, Philadelphia |
P.9260.133 |
226 |
Pier 78, South Delaware Wharves, north side, looking east, showing earth fill.
March 28, 1917 | Work completed
to date: 65.0%. Date of completion 18 months from February 16, 1916. Contract
No. 244 | P.9260.134 |
370 | Pier 78 South; superstructure,
inshore end, looking southeast. July 19, 1918 |
[work] completed to date: 95%. Contract No. 250 |
P.9260.135 |
406 |
Municipal Pier 78, south Delaware wharves, McKean Street, outshore end, looking
northwest. December 9, 1918 | |
P.9260.136 |
347 |
Pier 80 South; storage of steel for superstructure of Pier 9 North (Cherry
Street). May 28, 1918 | |
P.9260.137 |
530 |
Pier 82 South; driving piles, looking east. September 25, 1919 |
Work completed to date: 5.32%. Contract No. 344 |
P.9260.138 |
531 |
Pier 82 South; bulkhead north of pier, looking north. September 25, 1919 |
Work completed to date: 5.32%. Contract No. 344 |
P.9260.139 |
570 |
Pier 82 South; bulkhead north, looking northeast. November 21, 1919 |
Work completed to date: 12.20%. Contract No. 344 |
P.9260.140 |
598 |
Pier 82 South; piling north side, looking east. March 11, 1920 |
Work completed to March 20: 19.27% Contract No. 344 |
P.9260.141 |
720 |
Pier 82 South; piling, etc., north side, looking east. January 13, 1921 |
Work completed to January 20: 28.29%. Contract No. 344 |
P.9260.142 |
764 |
Pier 82 South; clamps, caps, piles, etc., looking east, south side. April 26,
1921 | Materials in place April 20th:
45.56%. Contract No. 344 | P.9260.143 |
817 |
Pier 82 South; bulkhead north of pier, looking west. July 20, 1921 |
Work completed to date: 78.68%. Contract No. 344 |
P.9260.144 |
818 |
Pier 82 South; south side of pier, bulkhead, etc., looking east. July 20, 1921 |
Work completed to date: 78.68%. Contract No. 344 |
P.9260.145 |
489 |
Pier 84 South; bulkhead section south of pier. June 20, 1919 |
Work completed to date: 2.62%. Contract No. 345 |
P.9260.146 |
506 |
Pier 84 South; bulkhead south of pier, looking north. August 21, 1919 |
Work completed to date: 12.2%. Contract No. 345 |
P.9260.147 |
507 |
Pier 84 South; looking northeast over site; showing dredge and pile drivers
at work. August 21, 1919 | |
P.9260.148 |
508 |
Pier 84 South; Ritner Street sewer, looking northeast, showing piling, etc.
August 21, 1919 | Work completed
to date: 12.2%. Contract No. 345 | P.9260.149 |
526 |
Pier 84 South; bulkhead south of pier, looking north. Sept. 25, 1919 |
Work completed to date: 18.16%. Contract No. 345 |
P.9260.150 |
527 |
Pier 84 South; looking northeast, showing piling south side of pier. Sept.
25, 1919 | Work completed to date:
18.16%. Contract No. 345 | P.9260.151 |
528 |
Pier 84 South; Ritner Street sewer, looking east. Sept. 25, 1919 |
Work completed to date: 18.16%. Contract No. 345 |
P.9260.152 |
546 |
Pier 84 South; bulkhead south of pier, looking north. Oct. 30, 1919 |
Work completed to Oct. 20: 21.08%. Contract No. 345 |
P.9260.153 |
569 |
Pier 84 South; looking northeast, showing piling, south side. Nov. 21, 1919 |
Work completed to date: 25.00%. Contract No. 345 |
P.9260.154 |
593 |
Pier 84 South; showing piling for tracks of pile cutting machine. Mar. 11,
1920 | Work completed to March 20:
32.92%. Contract 345 | P.9260.155 |
594 |
Pier 84 South; driving spur piles, south side, and framing. Mar. 11, 1920 |
Work completed to March 20: 32.92%. Contract 345 |
P.9260.156 |
595 |
Pier 84 South; platforms south side of pier, and bulkhead looking southeast,
Mar. 11, 1920 | Work completed to
March 20: 32.92%. Contract 345 | P.9260.157 |
596 |
Pier 84 South; showing joining of platforms, south side of pier bulkhead, top
view. Mar. 11, 1920 | Work completed
to March 20: 32.92%. Contract 345 |
P.9260.158 |
597 |
Pier 84 South; Ritner Street sewer, looking northeast. Mar. 11, 1920 |
Work completed to March 20: 32.92%. Contract 345 |
P.9260.159 |
637 |
Pier 84 South; south side, looking northwest; machine cutting off spur piles.
June 24, 1920 | Work completed to
June 20: 43.83%. Contract No. 345 |
P.9260.160 |
638 |
Pier 84 South; bulkhead, south side; concrete forms, etc., June 24, 1920 |
Work completed to June 20: 43.83%. Contract No. 345 |
P.9260.161 |
639 |
Pier 84 South; bulkhead, south side, looking southwest. June 24, 1920 |
Work completed to June 20: 43.83%. Contract No. 345 |
P.9260.162 |
640 |
Pier 84 South; platform and bulkhead, south side of pier, looking east. June
24, 1920 | Work completed to June
20: 43.83%. Contract No. 345 | P.9260.163 |
641 |
Pier 84 South; driving spur piles, south side of pier, June 24, 1920 |
Work completed to June 20: 43.83%. Contract No. 345 |
P.9260.164 |
658 |
Pier 84 South; irregular steel form, looking north. July 27, 1920 |
Work completed to July 20: 48.22%. Contract No. 345 |
P.9260.166 |
659 |
Pier 84 South; showing earth fill in center of pier, looking east. July 27,
1920 | Work completed to July 20:
48.22%. Contract No. 345 | P.9260.167 |
717 |
Pier 84 South; concrete cross wall, south side. Jan. 13, 1921 |
Work completed to Jan. 20: 68.73%. Contract No. 345 |
P.9260.168 |
718 |
Pier 84 South; south side of pier, inshore end. Jan. 13, 1921 |
Work completed to Jan. 20: 68.73%. Contract No. 345 |
P.9260.169 |
719 |
Pier 84 South; Ritner Street sewer, looking east. Jan. 13, 1921 |
Work completed to Jan. 20: 68.73%. Contract No. 345 |
P.9260.170 |
730 |
Pier 84 South; piling north side, etc., looking east. Feb. 17, 1921 |
Material in place Jan. 20: 68.73%. Contract No. 345 |
P.9260.171 |
731 |
Pier 84 South; north side Pier 84 and south side Pier 82; piling etc., Feb.
17, 1921 | Material in place Jan.
20: 68.73%. Contract No. 345 | P.9260.172 |
732 |
Pier 84 South; showing retaining wall south side, fill, etc. Feb. 17, 1921 |
Material in place Jan. 20: 68.73%. Contract No. 345 |
P.9260.173 |
759 |
Pier 84 South; retaining wall south side of pier. Apr. 26, 1921 |
Materials in place April 20: 79.93%. Contract No. 345 |
P.9260.174 |
760 |
Pier 84 South; forms for retaining wall, north side, outshore end. Apr. 26,
1921 | Materials in place April 20:
79.93%. Contract No. 345 | P.9260.175 |
762 |
Pier 84 South; clamps, caps, piles, etc. north side and bulkhead, Apr. 26,
1921 | Materials in place April 20:
79.93%. Contract No. 345 | P.9260.176 |
763 |
Pier 84 South; bulkhead north of pier; clamps, caps, piles, etc., Apr. 26,
1921 | Materials in place April 20:
79.93%. Contract No. 345 | P.9260.177 |
809 |
Pier 84 South; sewer, bulkheads and north side of pier, June 20, 1921 |
Work completed to date: 93.88%. Contract 345 |
P.9260.178 |
811 |
Pier 84 South; bulkhead and north side of 84, inshore end, looking east. June
20, 1921 | Work completed to date:
93.88%. Contract 345 | P.9260.179 |
812 |
Pier 84 South; retaining wall, north side, outshore end, looking west. June
20, 1921 | Work completed to date:
93.88%. Contract 345 | P.9260.180 |
819 |
Pier 84 South; bulkhead between piers 82 and 84, looking east. July 20, 1921 |
Work completed to date: 96.95%. Contract 345 |
P.9260.181 |
820 |
Pier 84 South; north side, inshore end, platform, etc., looking north. July
20, 1921 | Work completed to date:
96.95%. Contract 345 | P.9260.182 |
821 |
Pier 84 South; north side, bulkhead, sewer, etc., looking north. July 20, 1921 |
Work completed to date: 96.95%. Contract 345 |
P.9260.183 |
1188 |
Pier 84 South; Porter Street, 1921 |
Work complete. | P.9260.184 |